Built in Import Wizard Templates

Contents

  1. Gantt templates
  2. Earned Value Templates
  3. Stoplight templates
  4. Status templates
  5. Dashboard templates
  6. Milestone templates
  7. Resource templates
  8. Summary templates
  9. Special templates

Gantt templates

 
   

Basic Gantt

 

Like it's name implies, this is a basic Gantt chart format.  

The schedule is built using these imported fields: Start, Finish, Baseline Start and Baseline Finish.  

The task name and the task percent complete are shown in the columns.  

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Basic Gantt 2

 

This is a basic Gantt chart format.

From Microsoft Project, Milestones brings in percent complete.  A percent% pie symbol enhances this column.

The schedule is built using these imported fields: Start, Finish, Baseline Start and Baseline Finish.  

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Critical Tasks

 

This format will bring in only tasks which are marked Critical in the imported project. It is built using these imported fields: Start, Finish, Baseline Start and Baseline Finish.  

The following fields are brought into columns on the left side of the schedule: WBS, and Name

The following fields are brought into columns on the right side of the schedule: Percent Complete, Cost, Remaining Cost, and Resource

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Detailed Gantt

 

This format is more detailed (includes more information) than the Basic Gantt format.  

The following fields are brought into columns on the left side of the schedule: % Complete, WBS, Name

The following fields are brought into columns on the right side of the schedule: Cost, Remaining Cost, Actual cost and Resource Initials

The schedule is built using these imported: Start, Finish, Baseline Start and Baseline Finish. 

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



No Columns

 

As it's name implies, this choice brings in no columns.

The schedule is built using these imported fields: Start, Finish, Baseline Start and Baseline Finish.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Roadmap

 

Roadmap uses the imported project Name, and Percent Complete fields and imports that information into columns on the left side of the Milestones schedule area.

From Microsoft Project, Milestones brings in the numeric percent complete with a percent complete pie symbol.  .  

On the schedule, task names are shown as boxed symbols.

The import will bring into the schedule area Start, Finish, Baseline Start, Baseline Finish and dependencies.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Baseline with Actuals plus status

 

This format uses the imported project's Unique ID, Name, Baseline Start Baseline Finish Start and Finish and imports that information into columns on the left side of the Milestones schedule area.

This format uses the Microsoft Project Finish 5,and imports that information into column on the right side of the Milestones schedule area.

Milestones reads the imported Finish 5 date as status and the percent complete column reflects that status.  

The import will bring into the schedule area Start, Finish, Baseline Start, Baseline Finish and Finish 5.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Wall Sized Gantt

 

The wall sized format creates a schedule which is 44" by 22".  It uses these fields to build the schedule: Start, Finish, Baseline Start and Baseline Finish.  

This format uses the imported project's Percent Complete and Name fields.  These are imported into columns on the left side of the Milestones schedule area.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Multiple Baselines

 

This import format will bring in the current start and finish dates plus up to 9 baselines from Microsoft Project.  Choose the baselines to display from Microsoft Project's baselines.  (Baseline, Baseline 1..... Baseline 10).

This format is only available when importing from Microsoft Project.

x Can not be refreshed.

x Cannot be customized and used for a custom template.

 Project is required.



 

Earned Value Templates

 
   

Graph on Schedule (timephased)

This Import Wizard choice produces:

All columns are from Microsoft Project (no Milestones calculations on this chart).

Left Columns -1) Percent Complete,  2) Task Name

Right Columns - 1) Baseline Cost (from Project), 2) ACWP from Project, 3) BCWP from Project, 4) BCWS from project, 5) EAC from Project

Graph: Baseline Cost, EV, PV and AC from Project.  EV is BCWP and PV is BCWS.  Values are TimeScaled.  On the first screen of the wizard, choose how much granularity to use (daily, weekly, monthly, quarterly).

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



Graph Below Schedule (timephased)

 

This Import Wizard choice produces:

All columns are from Microsoft Project (no Milestones calculations on this chart).

Left Columns - 1) Task Name, 2) Percent Complete, 3) Baseline Finish

Right Columns - 1) BCWS (from Project), 2) BCWP from Project, 3) ACWP from Project, 4) EAC from project, 5) Baseline Cost from Project

Graph: EV is BCWP from Project and PV is BCWS from Project.  Values are TimeScaled.  On the first screen of the wizard, choose how much granularity to use (daily, weekly, monthly, quarterly.)

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



Performance Indicators (timephased)

 

This Import Wizard choice produces:

Column on the left: Task Name, Current Finish (Project Finish Date) and Baseline Finish (Project Baseline Finish Date)

Columns on the right: Project BCWS, BCWP and ACWP fields

Graph 1 - PV (Project BCWS field), EV (Project BCWP field) and AC (Project ACWP field)

Graph 2 - SPI and CPI from Microsoft Project

Values are TimeScaled.  On the first screen of the wizard, choose how much granularity to use (daily, weekly, monthly, quarterly.)

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



Current Vs Expected Costs (timephased)

 

This Import Wizard choice produces:

Columns on the left: Percent Complete, Task Name.

Columns on the right: Baseline Cost, EAC, BCWS, BCWP, ACWP.

Graph: Baseline Cost and AC (Actual Cost), TimeScaled Values from Microsoft Project.

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



EV Plus Remaining Funds (timephased)

 

This Import Wizard choice produces:

All columns are from Microsoft Project (no Milestones calculations on this chart).

Left Columns - % Complete, SV, CV, Name

Right Columns - BAC, PV, AC, EV

Graph: EV is BCWP from Project and PV is BCWS from Project.  Values are TimeScaled.  On the first screen of the wizard, choose how much granularity to use (daily, weekly, monthly, quarterly.)

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



EV SPI Percentage Bar

 

Specify either a number field or a date field on the last screen of the wizard. If a date field is specified, this field will be used to set the status for each task.

If a number field is specified (Number 1, 2 ...Number 20, or SPI) then a percent complete is calculated based on the calendar days from the start of the task to the status date divided by the total duration of the task.  The result of this calculation is then multiplied by the value in the number field.  This result is used to set the status for the task.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Performance Review (timephased)

 

This Import Wizard choice produces:

Column on the left: % Complete, SV, CV and Task Name

Columns on the right: Baseline Cost, BCWS, ACWP, BCWP and EAC

Graph: PV (Project BCWS field), EV (Project BCWP field), Baseline Cost, and AC (Project ACWP field)

Values are TimeScaled.  On the first screen of the wizard, choose how much granularity to use (daily, weekly, monthly, quarterly.)



Performance Review 2 (timephased)

 

This Import Wizard choice produces:

Left Columns - SPI, CPI, EAC, Task Name

Right Columns - Project BCWS, ACWP, BCWP, and % Complete fields

Graph - PV (Project BCWS field), EV (Project BCWP field), Baseline Cost, and AC (Project ACWP field)



CPI SPI EV Fields (timephased)

 

Earned Value - CPI, SPI and Other EV Fields

This is a good format for displaying earned value fields.

Columns on the left side of schedule: EAC, Task Name, Finish, Baseline Finish

Columns on the right side of schedule: BCWS, BCWP, ACWP, Baseline Cost, Cost 

All fields are from Microsoft Project.  Graph shows timescaled values from Microsoft Project.

 



Earned Value Dashboard

 

On the schedule: baseline and normal start/finish bars.  Also, on the schedule, a graph representing Budget, Actual Cost, Earned Value (BCWP) and Planned Value (PV or BCWS)

In the columns: - Schedule Variance and Cost Variance columns are shaded based on the values.  Green for value > 0, Red for value < 0 and Yellow for value = 0.  CPI displays an red indicator if the CPI is less than 1, Yellow if the CPI is between 1 and 1.3 and Green if the CPI is greater than 1.3."

Earned value for this schedule is calculated by Milestones Professional using Baseline Cost, Percent Complete and Actual Cost from Microsoft Project.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.

 



Condensed Earned Value

 

Columns on the left: 1) Name 2) Budget (Project Baseline Cost field), 3) Actual Cost, 4) PV (Calculated by Milestones), 5) EV (Calculated by Milestones)

Columns on the right: 1) SV, Schedule Variance, Calculated by Milestones, 2) CV, Cost Variance, Calculated by Milestones, 3) SPI, calculated by Milestones, 4) CPI, calculated by Milestones, 5) Percent Complete (from Project)           

Graph: Non-Timescaled PV, EV, Baseline Cost and AC calculated by Milestones Professional

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



 

Stoplight templates

 

Cost and Schedule Stoplight

 

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

This format uses the Microsoft Project Cost Variance and Status fields and imports that information into a single column on the right side of the Milestones schedule area.

Milestones converts the Microsoft Project information into stoplights.

On the Milestones Professional schedule, the red circle represents task that are behind and over cost. The green circle represents task that costs and schedule are OK. the yellow circle  represents task that are behind and cost is OK.  The blue circle represents task that are complete and cost is OK.

 Can be refreshed.

 Can be customized and used for a custom template.



Cost Variance 1

 

This Import Wizard choice produces:

On the left, two columns 1) % complete and 2) Task Name

On the right, three columns 1) Baseline Cost, 2) Actual Cost, and 3) A simple calculation column which subtracts Actual Cost from Baseline Cost.

Stoplights are displayed based on whether the Actual Cost exceeds the Baseline Cost.\

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Cost Variance 2

 

This Import Wizard choice produces:

On the left, one column: Task Name

On the right, three columns 1) ACWP, 2) BCWP and 3) CV with Red, Green Yellow stoplight indicators as described in the legend.

No calculations are done.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



 

Stoplight Indicators

 

This import format is an excellent one for viewing at-a-glance the health of a project.  This is accomplished using Milestones Professional's stoplight and indicator symbols.

On the Milestones Professional schedule, the cost variance information is converted to stoplight indicators:

On the Milestones Professional schedule, the status information is converted to indicators:

The following fields are brought into columns on the left side of the schedule:  Name field

The following fields are brought into columns on the right side of the schedule: Cost Variance and Status fields

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.

 



Stoplight using a number field

 

This template offers an ad-hoc way to generate indicators.  The Status column, which is set up with indicators, will come in EMPTY.  Then, enter values 1 through 9 to generate stoplights for the schedule, and update the legend according to entries.

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.

 



Stoplight Variety

 

As its name implies, Stoplight Variety offers a variety of stoplights.

The following fields are brought into columns on the left side of the schedule: Name, Duration, Remaining Duration, % Complete

The following fields are brought into columns on the right side of the schedule: Status (with Stoplight), Baseline Cost, Actual Cost and Cost Variance (with Indicator)

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

On the Milestones Professional schedule, the cost variance information is converted to indicators:

On the Milestones Professional schedule, the status information is converted to indicators:

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



Roadmap with Indicators

 

This format uses the Microsoft Project Name, Baseline Cost, Actual Cost, Percent Complete, and Finish Variance fields and imports that information into columns on the left side of the Milestones schedule area.

From Microsoft Project, Milestones brings in the numeric percent complete with a percent complete pie symbol.  

From Microsoft Project Milestones looks at the numeric Finish Variance then adds an indicator.

A special column "Cost OK" is added to the left side of the Milestones schedule.  Milestones looks at the Baseline Cost and Actual Cost from Microsoft Project then adds an indicator based on the cost's status.

On the schedule, task names are shown as boxed symbols.

The import will bring into the schedule area Start, Finish, Baseline Start and Baseline Finish.

 Can be refreshed.

 Can be customized and used for a custom template.

 Project is required.



Remaining Duration

This format uses the Microsoft Project Name field and Resource Initials and imports that information into a column on the left side of the Milestones schedule area.

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

The Remaining Duration field is added to a column on the right of the schedule.  It includes an indicator with the following constraints:

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.

 



Variance Stoplights

 

This Import Wizard choice produces:

On the left, RGY(Red-Green-Yellow) Stoplight columns for Schedule Variance, Start Variance and Finish Variance, Task Name.

On the right,  RGY(Red-Green-Yellow) Stoplight columns for Cost Variance

On the schedule: Baseline start/finish and start/finish are shown.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Variance Stoplights 2

 

The far left column displays CRITICAL (shaded red) for tasks which are critical.

On the right,  RGY(Red-Green-Yellow) Stoplight columns for Variances: Start, Finish, Cost, Work and Duration.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Finish Variance

 

This format uses the Microsoft Project Name, Finish VarianceFinish Variance, Baseline Finish and finish fields and imports that information into columns. Name, and  Finish VarianceFinish Variance import into columns on the left side and Baseline Finish and Finish imports into columns on the right side of the Milestones schedule.

Milestones converts the Microsoft Project Finish Variance information into indicator symbols.

All finish variances greater than zero is considered Ahead of Schedule and depicted by a green circle.

All finish variances  less than zero is considered Behind Schedule and depicted by a red circle.

All finish variances equal to zero is considered On Schedule and depicted by a yellow circle.

This format will bring into the schedule area Microsoft Project fields Finish and Baseline Finish as milestones and Summary Tasks as a start date milestone, horizontal connector, end date milestone.

 Can be refreshed.

 Can be customized and used for a custom template.

  MPP, XML, XER, BK3.



Finish Variance 2

This format uses the Microsoft Project Name, Finish, Baseline Finish, and Finish Variance fields and imports that information into columns on the schedule.  Name, Finish and Baseline Finish fields are imported on the left side of the Milestones schedule area.

  • In the Finish Variance column, Milestones converts the Microsoft Project Finish Variance information into indicator symbols.

  • All finish variances greater than zero is considered Ahead of Schedule and depicted by a green circle.

  • All finish variances  less than zero is considered Behind Schedule and depicted by a red circle.

  • All finish variances equal to zero is considered On Target and depicted by a yellow circle.

This format will bring into the schedule area Microsoft Project fields Finish and Baseline Finish as milestones, using the symbols in the first row of the toolbox.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.

 



 

Status templates

 

Status Stoplight

This format uses the Microsoft Project Status field and imports that information into a column on the right side of the Milestones schedule area. Milestones converts the Microsoft Project status field information into indicator symbols:

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

 Can be refreshed.

 Can be customized and used for a custom template.



Slipping Tasks

This Import Wizard choice produces:

"On the left, Task Name, Baseline Start, Start, Baseline Finish, Finish

The schedule shows tasks which are behind schedule.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Unstarted Tasks

The Unstarted Tasks report displays all tasks which do not have an actual start date.  A chart is produced showing the WBS # and Task name in the left columns.  

To the right of the schedule, indicators will show whether a task is critical and also whether or not the task is late.



Status Line

This Import Wizard choice produces:

On the left, Task Names

On the right, Percent Complete

Status Line is drawn to illustrate % complete (status) for each task.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Top Level Tasks

This Import Wizard choice produces:

On the left: WBS and Task Name.

On the right, Schedule and Cost indicators as shown in the legend, plus a %complete Pie Indicator column."

x Can not be refreshed.

 Can be customized and used for a custom template.



Weekly Status Report

Weekly Status Report, provides a simple format with easy to read information for a quick status of multiple tasks.

 Can be refreshed.

 Can be customized and used for a custom template.

 MPP, XML, XER, BK3.



Cost Account Plan

This is a common defense industry format which can be easily customized to meet reporting requirements.

Column on the left: 1) Name, Finish, Baseline Finish, Finish Variance

Columns on the right: BCWS, BCWP from Microsoft Project

Graph: Timescaled PV and EV (BCWS and BCWP) from Microsoft Project

 

 Can be refreshed.

 Can be customized and used for a custom template



Project Status Report

This Import Wizard choice produces:

Left Columns - WBS, Task Name

Right Columns - Duration, Remaining Duration, Remaining Duration%, Cost, Remaining Cost, Remaining Cost %, Resource Names.

Baseline start/finish and start/finish are shown

 

 Can be refreshed.

 Can be customized and used for a custom template



 

Dashboard templates

 

Project Dashboard

 

On the schedule: baseline and normal start/finish bars.  Also, on the schedule, a graph representing Budget, Actual Cost and Earned Value (BCWP)."

In the columns: - name, baseline and actual cost, percent complete, BCWP, cost variance (CV) and Cost Performance Index (CPI).  An indicator for CPI displays Red for CPI less than 1, Green for CPI 1.3 or higher and Yellow for CPI between 1 and 1.3"

Note:

  • Earned Value comes directly from Microsoft Project.  However, instead of the timescaled values, Milestones Professional distributes the values across each task.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Project Funding Dashboard

On the schedule: baseline and normal start/finish bars.

On the graph below schedule: budget vs/actual cost for each month."

In the columns: a stoplight displays Red-Green-Yellow stoplight indicator based on the Microsoft Project Remaining Cost field.  If Remaining Cost is greater than zero, a green indicator is shown.  If Remaining Cost is zero, the indicator is yellow.  If Remaining Cost is less than zero, a red indicator is shown meaning funds are exhausted.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3



Dashboard Chart 4

In the schedule: baseline and normal start/finish bars.  Also, on the schedule, a graph representing Budget, Actual Cost and Earned Value (BCWP)."

In the columns: - name, baseline and actual cost, Cost Performance Index (CPI), percent complete, earned value, cost variance (CV).  An indicator for CPI displays Red for CPI less than 1, Green for CPI 1.3 or higher and Yellow for CPI between 1 and 1.3" From Microsoft Project Milestones brings in the numeric percent complete then adds a percent complete pie symbol.  

Note: Earned Value comes directly from Microsoft Project.  However, instead of the timescaled values, the values are distributed across each task using Microsoft Project values for each task.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Dashboard Chart 5

Earned value calculation for this chart:  Milestones Earned Value

On the schedule:

baseline start/finish and start/finish.  

A graph showing PV, EV, BAC and AC.  Baseline Cost, Actual Cost and Percent Complete are from Microsoft Project.  All other earned value information on this graph is calculated by Milestones Professional. "

In the columns

On the right: Cost, Remaining Cost, Actual Cost and Resource Initials"

The Microsoft Project start+finish and baseline start+finish are imported"

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Earned Value Dashboard

On the schedule: baseline and normal start/finish bars.  Also, on the schedule, a graph representing Budget, Actual Cost, Earned Value (BCWP) and Planned Value (PV or BCWS)

In the columns: - Schedule Variance and Cost Variance columns are shaded based on the values.  Green for value > 0, Red for value < 0 and Yellow for value = 0.  CPI displays an red indicator if the CPI is less than 1, Yellow if the CPI is between 1 and 1.3 and Green if the CPI is greater than 1.3."

Earned value for this schedule is calculated by Milestones Professional using Baseline Cost, Percent Complete and Actual Cost from Microsoft Project.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Dashboard Summary Chart

In the schedule: Baseline and Normal Start/Finish bars.  

A graph representing Budget and Actual Cost.

In the columns: On Time indicator (Milestones calculation column baseline end minus end date), Cost OK indicator (Milestones calculation column baseline minus costs to date), Percent Complete, Who (Microsoft, Baseline Cost, Cost to Date (Microsoft actual cost)

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



 

 

Milestone templates

 

Date Comparison

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

This format will bring into the schedule area Microsoft Project fields Start, Finish, Baseline Start, Baseline Finish, Actual Start, Actual Finish, and Deadline along with Summary Tasks.

Start and Finish date will be depicted in the Milestones schedule area as a symbols. They will be drawn using symbols in the second row of the toolbox.

Baseline Start and Baseline Finish will be depicted in the Milestones schedule area as a symbols.  They will be drawn using the symbols in the 3rd row of the toolbox.

Actual Start and Actual Finish will be depicted in the Milestones schedule area as a symbols. They will be drawn using the symbols in the 4th row of the toolbox.

Summary bars use the first row of the toolbox.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



 

Finish Dates

The Microsoft Project Name field is imported into a column on the left side of the Milestones schedule area.

This format will bring into the schedule area Microsoft Project fields Finish milestones at the lowest level and Summary tasks based on lower level tasks.

Finish milestones are shown using the first symbol on row 2 of the toolbox.

Summary bars use the symbols and bars found in the first row of the toolbox.  Both symbols are "null" or blank symbols (type 28).

Any task marked Critical in Microsoft Project will be colored red on the resulting Milestones Professional schedule. The right most symbol on row 2 of the toolbox is used for this purpose.

 Can be refreshed.

 Can be customized and used for a custom template



Finish Dates Rolled Up

This format uses the Microsoft Project Name, Finish and Percent Complete fields and imports that information into a columns. Name and Finish import into columns on the left side and Percent Complete imports into columns on the right side of the Milestones schedule.

This format will bring into the schedule area Microsoft Project fields Finish milestones at the lowest level and Summary tasks based on lower level tasks. Finish date milestones roll up to the summary bars.

Finish milestones use symbol 3 in the toolbox.

Summary bars use symbol 1 and symbol 2 along with horizontal bar 1 in the toolbox. Both symbols are null symbols.

Any task marked Critical in Microsoft Project will be colored red on the resulting Milestones Professional schedule. Symbol 4 in the toolbox is used for critical milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Finish Dates Plus Status

This format uses the Microsoft Project Name and Percent Complete and imports that information into separate columns on the left side of the Milestones schedule area.

From Microsoft Project, Milestones brings in the numeric percent complete with a percent complete pie symbol.

On the Milestones Professional schedule, the status column uses the information from the %complete column and converts it to indicators. Red circle represents task that have not started. Green circle represents task that are in progress.  Black check mark represents task that are complete.

This format will bring into the schedule area Microsoft Project field Finish milestones at the lowest level and Summary tasks based on lower level tasks.

Finish milestones use symbol 3 in the toolbox.

Summary bars use symbol 1 and symbol 2 along with horizontal bar 1 in the toolbox. Both symbols are null symbols.

Any task marked Critical in Microsoft Project will be colored red on the resulting Milestones Professional schedule. Symbol 4 in the toolbox is used for critical milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Finish Variance

This format uses the Microsoft Project Name, Finish VarianceFinish Variance, Baseline Finish and finish fields and imports that information into columns. Name, and  Finish VarianceFinish Variance import into columns on the left side and Baseline Finish and Finish imports into columns on the right side of the Milestones schedule.

Milestones converts the Microsoft Project Finish Variance information into indicator symbols.

All finish variances greater than zero is considered Ahead of Schedule and depicted by a green circle.

All finish variances  less than zero is considered Behind Schedule and depicted by a red circle.

All finish variances equal to zero is considered On Schedule and depicted by a yellow circle.

This format will bring into the schedule area Microsoft Project fields Finish and Baseline Finish as milestones and Summary Tasks as a start date milestone, horizontal connector, end date milestone.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Finish Variance 2

This format uses the Microsoft Project Name, Finish, Baseline Finish, and Finish Variance fields and imports that information into columns on the schedule.  Name, Finish and Baseline Finish fields are imported on the left side of the Milestones schedule area.

  • In the Finish Variance column, Milestones converts the Microsoft Project Finish Variance information into indicator symbols.

  • All finish variances greater than zero is considered Ahead of Schedule and depicted by a green circle.

  • All finish variances  less than zero is considered Behind Schedule and depicted by a red circle.

  • All finish variances equal to zero is considered On Target and depicted by a yellow circle.

 

This format will bring into the schedule area Microsoft Project fields Finish and Baseline Finish as milestones, using the symbols in the first row of the toolbox.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Project Report

This format uses the Microsoft Project Percent Complete, Name, Start, Finish and Cost fields and imports that information into a columns. Percent Complete and Name import into columns on the left side and Start, Finish and Cost import into columns on the right side of the Milestones schedule.

This format will bring into the schedule area Microsoft Project fields Finish milestones at the lowest level and Summary tasks based on lower level tasks.

Finish milestones use symbol 3 in the toolbox.

Summary bars use symbol 1 and symbol 2 along with horizontal bar 1 in the toolbox. Both symbols are null symbols.      

Any task marked Critical in Microsoft Project will be colored red on the resulting Milestones Professional schedule. Symbol 4 in the toolbox is used for critical milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Scatter Chart

     

This is a summary format that brings in summary bar start and finish using the symbols and bars on row 8 of the toolbox.

If the summary bars have lower level task, the task come in as finish milestones. During the import choose how many milestones to see per task row.  Also, pick from several Microsoft Project fields to have symbol text associated with the milestones. Milestones colors the milestones symbol and its accompanying text the same color. Symbols 1 and 2 of the toolbox are used for the milestones. The color used for each milestone is an override ride

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Zero Duration Tasks

T

his format uses the Microsoft Project Name, WBS, and Finish  fields and imports that information into a columns. Name and WBS import into columns on the left side and Finish import into columns on the right side of the Milestones schedule.

This format will bring into the schedule area Microsoft Project tasks marked as milestones (milestones have zero duration).

The milestone tasks will be depicted in the Milestones schedule area as a symbol. It will be drawn using the 3rd symbol in the toolbox.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 

   


 

Resource templates

 
   


Resource Summary

 

This format uses the Microsoft Project Resource, Cost and Work fields importing that information into columns on the left and right sides of the Milestones schedule area.

The import will brings into the schedule area a summary of the resources projects by showing a start symbol on the first day of the resources' projects, connecting with a horizontal bar to an end symbol depicting the last day of the resources' projects.

The import uses the Cost and Work columns to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. It creates a DataGraph at the bottom of the schedule showing Cost and Work. See Making changes to DataGraphs

x Can not be refreshed.

x Cannot be customized and used for a custom template



Tasks By Resource

This format uses the Microsoft Project WBS, Name, Cost and Work fields importing that information into columns on the left and right sides of the Milestones schedule area.

Each resource's task are grouped together.

The import will brings into the schedule area each task showing a start symbol on the first day of the task connecting with a horizontal bar to an end symbol depicting the last day of the task.

In the schedule area Milestones Professional draws a summary bar for each resource based on the Resources' tasks.

The import uses the Cost and Work columns to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. A bar DataGraph is creating, showing Cost and Work.

x Can not be refreshed.

x Cannot be customized and used for a custom template



Tasks By Resource 2

This format uses the Microsoft Project Name, Resource, Work, Actual Work and Percent Complete fields importing that information into columns on the left and right sides of the Milestones schedule area.

Resource brings into the schueld the task and under each task the resource responsible for that task.

The import will brings into the schedule area for each resource the start date and end date of its work for that task.

In the schedule area Milestones Professional draws a summary bar reflecting all the tasks' resource work.

x Can not be refreshed.

x Cannot be customized and used for a custom template



Overallocated

This format uses the Microsoft Project Name, Peak and Work fields importing that information into columns on the left and right sides of the Milestones schedule area.

The import will brings into the schedule area any resource that is over allocated.

In the schedule area Milestones Professional draws a summary bar reflecting all the resource's tasks.

To view the detail for a particular resource on this chart, right-click the resource name and choose Expand Selected Task Row.  All the resource's tasks will be listed showing a start symbol on the first day of the task connecting with a horizontal bar to an end symbol depicting the last day of the task.

The import uses the Work column to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. A bar DataGraph is created showing Work. 

x Can not be refreshed.

x Cannot be customized and used for a custom template



Tasks by resource detailed

This format uses the Microsoft Project Task ID, Name, Duration, Start, Finish, Percent Complete Cost and Work fields importing that information into columns on the left and right sides of the Milestones schedule area.

The import will brings into the schedule area under the each of the resources their tasks showing a start symbol on the first day of the task connecting with a horizontal bar to an end symbol depicting the last day of the task.

In the schedule area Milestones Professional draws a summary bar reflecting all the resource's tasks.

The import uses the Cost and Work columns to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. A bar DataGraph is added at the bottom of the schedule showing Cost and Work.

See Making Changes to DataGraphs.

x Can not be refreshed.

x Cannot be customized and used for a custom template



Unstarted Tasks By Resource

 This Import Wizard choice produces:

 A list of un-started tasks for each resources, indicating (with a check) which resources are over allocated.

 

x Can not be refreshed.

x Cannot be customized and used for a custom template



Single Resource

During the import process the wizard offers a list of resources to select.

This format uses the Microsoft Project WBS, Name, Cost and Work fields and imports that information into columns on the left and right sides of the Milestones schedule area.

The import brings into the schedule area each of the chosen resource tasks showing a start symbol on the first day of the task connecting with a horizontal bar to an end symbol depicting the last day of the task.

In the schedule area Milestones Professional draws a summary bar reflecting all the resource's tasks.

The import uses the Cost and Work columns to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. A bar DataGraph is created showing Cost and Work.  See Making Changes to DataGraphs.

x Can not be refreshed.

x Cannot be customized and used for a custom template

 



Work variance

This format uses the Microsoft Project WBS, Resources, Scheduled Work, Baseline Work, and Work Variance fields importing that information into columns on the left and right sides of the Milestones schedule area.

Milestones converts the Microsoft Project Work Variance information into indicator symbols.

  • Tasks with less work scheduled than originally planned will show a down arrow.

  • Tasks with more work scheduled than originally planned will show an up arrow.

  • Tasks with work scheduled = work will show a check mark.

The import will brings into the schedule area each resources' task showing a start symbol on the first day of the task connecting with a horizontal bar to an end symbol depicting the last day of the task.

 Can be refreshed.

 Can be customized and used for a custom template

   


 

Summary templates

 


Presentation Timeline 

 

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

The import will bring into the schedule area Summary tasks Start and Finish and rolled up finish dates of their respective sub-tasks. At the lowest sub-task level  Start, Finish and Milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



 Presentation Timeline Angled Text

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

The import will bring into the schedule area Summary tasks Start and Finish and rolled up finish dates of their respective sub-tasks. At the lowest sub-task level  Start, Finish and Milestones.

Text associated with the Finish date will come into the Milestones schedule at an angle on the summary bar.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



Compact Gantt

This format uses the Microsoft Project Unique ID and Name fields and imports that information into columns on the left side of the Milestones schedule area.

The import will bring into the schedule area Summary tasks Start, Finish, Baseline Start, and Baseline Finish. Lower level Start, Finish, Baseline Start, and Baseline Finish.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 

 



Cost Summary With Graph

This format uses the Microsoft Project ID, Name, Baseline Cost, Cost and Resource Initials fields and imports that information into columns on the Milestones schedule. ID and Name are imported on the left side of the Milestones schedule area. Baseline Cost, Cost and Resource Initials are imported on the right side of the Milestones schedule area.

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

The import uses the Cost and Baseline Cost columns to set-up Type 3 ValueSets: Allocate Column Values Across Timeline. Creating a bar Datagraph at the bottom of the schedule comparing Cost and Baseline Cost. The alignment for Value Set is Weekly.  The graphic properties of the ValueSets and alignment can be changed using the Setup ValueSets options found on the Tools tab in Milestones. The properties of the Datagraph can be changed using the Setup Datagraph options found on the Tools tab in Milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 MPP, XML, XER, BK3

 



Compact Sequential Tasks

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

Milestones brings into the schedule area start and finish dates using symbol 1 and 2 in the toolbox and horizontal bar 1.

Any symbol text information is associated with the start symbol and is centered on horizontal bar.

The lower level information is displayed on a summary row.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



Condensed Finish Dates

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

Milestones brings into the schedule area the start and finish dates connected with a horizontal bar.

The finish dates are copied up onto the summary row in a scatter pattern to prevent overlapping as much as possible.

Any Microsoft Project tasks that are critical will show red finish dates on the summary rows.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



Space Saver

The purpose of this format is to display as many tasks as possible on as few rows as possible without collision. Schedules with many dates very close together may collide, still. Increasing the width of the schedule may help spread-out the symbols.

This format uses the Microsoft Project Name field and imports that information into a column on the left side of the Milestones schedule area.

The import will bring into the schedule area Start date, Finish Date and Milestones.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



Top Level With Cost Plus Work

This import format is similar to Basic Gantt, with the addition of Cost and Work.

The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish.  

The following fields are brought into columns on the left side of the schedule: ID and Name

The following fields are brought into columns on the right side of the schedule: % Complete, Cost and Work

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.

Scatter Chart

This is a summary format that brings in summary bar start and finish using the symbols and bars on row 8 of the toolbox. During the import, choose how many milestones to see per task row.  Also, pick from several Microsoft Project fields to have symbol text associated with the milestones. Milestones colors the milestones symbol and its accompanying text the same color. Symbols 1 and 2 of the toolbox are used for the milestones. The color used for each milestone is an override.

 Can be refreshed.

 Can be customized and used for a custom template

 Project must be installed.



 

 

 

Special templates

 

Work Remaining Vs Money Remaining

In the schedule: Baseline Start/Finish bars and normal Start/Finish bars.  

In the columns: Name, Indicator (Milestones calculation column % Cost Remaining minus % Work Remaining), % Cost Remaining (Milestones calculation column Remaining Cost divided by Cost), % Work Remaining (Milestones calculation column Remaining Work divided by Work)

x Can not be refreshed.

x Cannot be customized and used for a custom template

 Project must be installed.



 Percent Complete Bar Graph

This format shows the percent complete for each task as a bar.

x Can not be refreshed.

x Cannot be customized and used for a custom template

 Project must be installed.



 

 

 

 

 

 

Related Topics

  1. Build a Free Form Presentation Chart and Update it with Primavera dates
  2. Working with Microsoft Project

 

 

 

 

 

  

Guided Help Home

 

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2025 KIDASA Software, Inc. All rights reserved.